During the last month at Depot we have been finalising the fit out from units 01 – 25. Unit 26 – 35 have been sheeted, flushed and kitchen fit out.

Externally the scaffold has been stripped on the North, East and South elevation. West elevation scaffold has been erected ready for texture 

Over the next 4 weeks:

Unit 01 – 25 will see the final silicone, carpet installation and builders clean.

Unit 26 – 35 will see the 2nd fix and timber flooring installation.

Externally the North, South, East and West elevations texture coat and balustrade will be finalised.

Common area scaffold will be stripped for planter boxes to be completed.