Depot July 2015

Ground Floor

  • First coat of paint and cabinets are installed
  • Tiling is about to commence
  • Car stacker ready to commence next week

First Floor

  • First coat of paint and cabinets due to start on Monday 3rd 

Second Floor

  • Gyprock completed and Internal Painting to start

Third Floor

  • Gyprock flushing starting

Fourth Floor

  • Timber framing to second floor commencing next week 

Common Areas

  • Walkway linings and external façade works to commence next week