External Paving will be completed by the end of this week
Ground Floor: Main entry will be completed at the end of this week and units cleaned and currently being snagged
Car Stackers being commissioned this week
Level 1: Car park line marked 
First Floor: Units cleaned and currently being snagged
Second Floor: Units final clean this week
Third Floor: Units final clean this week
Fourth Floor: Units robe fit off this week along with the shower screen fit off
Common areas: Water proofing this week in preparation for tiling and landscaping