Psaros / News

Depot February 2015

  • Ground works are complete
  • Ground floor slab has been poured = final stage
  • Walls to ground to first floor are installed
  • Formwork to first floor complete
  • Reinforcement steel to first floor commenced
  • Ramp to first floor carpark progressing
  • Walls to second floor booked to be delivered to site