Ground Floor –Common Area : Car Stacker/ceilings to entry. Units 1- 3 shower screens and robes booked for later next week.

First Floor – shower screens/robes booked for end of next week

Second Floor – Cabinet install 90% complete, Stone bench top install commencing on Tuesday next week, continue with Tiling to bathrooms next week

Third Floor – Painting complete – start cabinet install next week

Loft Level – Currently installing roof trusses and fire rated linings – roof measure next week and starting box gutters later in the week.