Psaros / News

Corner September 2015

Basement: Western Power Transformer room live, Matera switch board installed, cable termination in progress for all apartments. Insulation commenced on ground floor soffit. Car stacker delivered and install commenced to ground floor car park. 

Level 1 (Units 1-8): Tilling completed, robe install commenced, lobby and hallway sheeted and Ritek flushed. Electrical and Hydraulic fit off 80% 

Level 2 (Units 9-16): Tilling completed, robe install commenced, lobby and hallway sheeted and Ritek flushed. Electrical and Hydraulic fit off 80% 

Level 3 (Units 17-24): Tiling 80%, electrical fit off 80% 

Level 4 (Units 25-32): Cabinets completed, WPM installed, Tiling to commence week starting 28/9/15 

Level 5 (Units 33 & 34): Wiring and tube out commenced, still waiting on fixture selections to be delivered to site to completed tube out. Aluminium doors completed.    

Roof Deck: Solar frame work completed, panel install week commencing 28/9/15. Mechanical and hydraulic install to roof competed.

Target for October is to bring the external finishes down both East and West elevations allowing the removal of scaffold from each of these areas. Removal of the tower crane 2/10/15. Commence instillation of lift. Continue with internal fit out working up progressively from 1st floor.