Corner October 2015

Basement: End of trip facilities screeded, all permanent lights installed, continue fit off electrical cabling, lift material delivered and install commenced.

Ground Floor: External tiling to façade commenced, lobby floor screeded, car stacker install completed.

Level 1 (Units 1-8): Painting 80%, shower screens and mirrors completed. Flooring levelling completed. Fit off complete. Splash backs complete, silicon complete. 

Level 2 (Units 9-16): Painting 80%, shower screens and mirrors completed. Floor levelling 50%. Splash backs 80%, 

Level 3 (Units 17-24): Painting 80%, Tiling complete, electrical fit of 80%. 

Level 4 (Units 25-32): Painting 80%, Tiling 90%, 

Level 5 (Units 33 & 34): All wall and ceiling frame work complete, sheeting 75%.     

External: Eastern elevation scaffold removed, southern elevation down to level 4 (excluding the hoist tower section), Western elevation to level 4. Northern wall and void texture coat 70%.  Balustrading down to level 3 on the western elevation.