Corner October 2014

The basement has been excavated to the reduced levels. The car stacker pit is being constructed and will be complete within the next week. The excavation works will commence next week for the lift overrun pit and crane base. Detailed excavation will be completed in the next month to enable the waterproof membranes to be installed.The basement slab will be poured by Christmas. Works are progressing well.