Work is continuing at a rapid pace at Corner.

The 4th floor slab has been poured and 50% of the structural walls for Level 4 Apartments are in place. Works have commenced to form the 5th floor slab which will be mid-June. The project is well on target to have the roof installed in July.

Internally the internal partitions have been installed on levels 1 & 2 with the electricians and plumbers now installing the services.

Within the car park areas the service installations are well underway with the main hydraulic services practically complete and 60% of the electrical services and lighting installed and working.

The car Stackers are being delivered from Germany next month and works to install will commence upon delivery.