Corner June 2015

Basement: Car Stacker installation in progress

Level 1 (Units 1-8): Gyprock lining in progress.

Level 2 (Units 9-16): Ready for Gyprock lining

Level 3 (Units 17-24): Ready for Gyprock lining

Level 4 (Units 25-32): Stripping formwork.

Level 5 (Units 33 & 34): Standing ritek walls

The aim for July is to have the roof frame fitted and started on roof cover. Internally we hope to have gyprock complete on levels 1 & 2.