Corner July 2015

Basement: Western Power Transformer room trench floor works underway, doors installed and mechanical works completed. Cables to get installed week starting 17/8/15 

Level 1 (Units 1-8): Flushing 90% complete, doors hung internally and entry doors to follow 1st week August, Painters to commence level 1 works Monday 3/8/15. Cabinets will begin install week starting 10/8/15.

Level 2 (Units 9-16): Gyprock lining under way 

Level 3 (Units 17-24): Ready for Gyprock lining 

Level 4 (Units 25-32): Framed and all tube out and pre wiring completed, ready for Gyprock

Level 5 (Units 33 & 34): Structural steel completed, roof to be installed week commencing 3/8/15 

Tiling to commence to all balconies week starting 3/8/15 with balustrade instillation to follow on directly. Frame work to Alucabond cladding has already commenced and panels will be installed once tiling has been completed.

Target for August is to bring the external finishes down both East and West elevations allowing the removal of scaffold from each of these areas. Continue with internal fit out working up progressively from 1st floor.