Basement: Western Power Transformer room, all cables drawn, additional plinth poured for transformer install. Doors and mechanical instillations completed.

Level 1 (Units 1-8): First coat of paint complete, cabinets, doors and skirting installed. Stone tops install to start. Common area ceiling framed up. Balcony tiles 90% complete.

Level 2 (Units 9-16): Spray coat to ceilings and walls completed, cabinets, doors and skirting installed, stone top templates supplied to Marbleman. 

Level 3 (Units 17-24): Gyprock flushing to be completed Wednesday 2/9/15 

Level 4 (Units 25-32): Gyprock commenced 25/8/15

Level 5 (Units 33 & 34): Roof completed 90%, waiting on flashing to be completed, wiring and tube out commenced, wall framing completed, aluminium doors 90% completed,    

Roof Deck: Solar to commence install Monday 31/8/15. Mechanical and hydraulic install to roof 90% competed.

Tiling to balconies and hob details completed, handrails to be installed week commencing 31/8/15.

Target for September is to bring the external finishes down the East and West elevations allowing the removal of scaffold from each of these areas. Continue with internal fit out working up progressively from 1st floor.