Works are progressing very well. The level 3 slab is now being formed and will be poured early next Month. We are currently planning to top out the building in late June, which is on program.

The works Internally are well underway, with the electrical services being installed to the basement level and ground floor levels.

Formwork is being removed to level 1 and  preparation is underway to commence the installation of the services.

Gyproc works will commence in the next 2 weeks along with door and window installations.