Bravo September 2014

Townhouses

The roof is  now installed as such it has allowed us to commence the external rendering to the building. Weather pending we will complete the rendering within the next 2 to 3 weeks.

Internally the plasterboard walls and ceilings are progressing. The next stage of works will be to commence installing the cabinets and tiling works.

Apartments

Roof cover is booked to commence early next week.

Internally, we have commenced installing the plasterboard walls and ceiling working our way up the building. The next stage will be to commence installing cabinets and tiling works