Bravo October 2014


All walls and ceilings are complete. Screeding  to wet areas are complete. Cabinets have commenced being installed. Tiling and paining has commenced.


All ceiling and walls complete except level 4. Screeding to wet areas complete except level 4. Cabinets have commenced being installed on level 1. Tiling and paining has commenced to level 1. Roof top deck is complete and waterproofing to commence this month. Approx. 80% of the external texturing is complete and we should complete all by the end of November.