Townhouses

  • Tiling complete to units 1 to 4 – progressing to units 5 & 6
  • Cabinets complete to units 1 to 4 – progressing to units 5 & 6
  • Timber flooring to units 1 & 2 to commence

Apartments

  • Cabinets installed to all apartments on level 1 & 2
  • Stone tops booked to complete install to units to level 1 & 2
  • Timber flooring has commenced to level 1
  • Level 3 plasterboard installed, flushing to commence
  • Commence tiling level 3